52.216-2 — Economic Price Adjustment—Standard Supplies.
Researched by the BidStride Research Team
What This Clause Requires
FAR 52.216-2 — Economic Price Adjustment—Standard Supplies.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.
Official Regulation Text
52.216-2 Economic Price Adjustment—Standard Supplies. As prescribed in 16.203-4(a), insert the following clause: Economic Price Adjustment—Standard Supplies (NOV 2021) (a) The Contractor warrants that the unit price stated in the Schedule for ____ [ offeror insert Schedule line item number ] is not in excess of the Contractor's applicable established price in effect on the contract date for like quantities of the same item. The term unit price excludes any part of the price directly resulting from requirements for preservation, packaging, or packing beyond standard commercial practice. The term established price means a price that (1) is an established catalog or market price for a commercial product sold in substantial quantities to the general public, and (2) is the net price after applying any standard trade discounts offered by the Contractor. (b) The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any applicable established price. Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased. The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor's established price, and this contract shall be modified accordingly. (c) If the Contractor's applicable established price is increased after the contract date, the corresponding contract unit price shall be increased, upon the Contractor's written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations: (1) The aggregate of the increases in any contract unit price under this clause shall not exceed 10 percent of the original contract unit price. (2) The increased contract unit price shall be effective (i) on the effective date of the increase in the applicable established price if the Contracting Officer receives
Compliance Checklist
- (b) The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any applicable established price.
- Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased.
- The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor's established price, and this contract shall be modified accordingly.
- (c) If the Contractor's applicable established price is increased after the contract date, the corresponding contract unit price shall be increased, upon the Contractor's written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations: (1) The aggregate of the increases in any contract unit price under this clause shall not exceed 10 percent of the original contract unit price.
- (2) The increased contract unit price shall be effective (i) on the effective date of the increase in the applicable established price if the Contracting Officer receives the Contractor's written request within 10 days thereafter or (ii) if the written request is received later, on the date the Contracting Officer receives the request.
- (3) The increased contract unit price shall not apply to quantities scheduled under the contract for delivery before the effective date of the increased contract unit price, unless failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause.
- (4) No modification increasing a contract unit price shall be executed under this paragraph (c) until the Contracting Officer verifies the increase in the applicable established price.
- (d) During the time allowed for the cancellation provided for in subparagraph (c)(5) above, and thereafter if there is no cancellation, the Contractor shall continue deliveries according to the contract delivery schedule, and the Government shall pay for such deliveries at the contract unit price, increased to the extent provided by paragraph (c) above.
Flow-Down to Subcontractors
No flow-down required
This clause applies only to the prime contract and does not need to be flowed down to subcontractors.
Frequently Asked Questions
FAR 52.216-2 (Economic Price Adjustment—Standard Supplies.) is a federal acquisition regulation clause that may be included in government contracts. It falls under the contract-types category.
FAR 52.216-2 is typically required when the contracting officer determines it's applicable to the specific procurement. Check the solicitation's Section I for included clauses.
Whether FAR 52.216-2 flows down depends on the specific clause language and contract type. Review the clause text for flow-down provisions.
This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.