What This Clause Requires

FAR 52.217-2 — Cancellation Under Multiyear Contracts.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.217-2 Cancellation Under Multiyear Contracts. As prescribed in 17.109(a), insert the following clause: Cancellation Under Multiyear Contracts (OCT 1997) (a) Cancellation, as used in this clause, means that the Government is canceling its requirements for all supplies or services in program years subsequent to that in which notice of cancellation is provided. Cancellation shall occur by the date or within the time period specified in the Schedule, unless a later date is agreed to, if the Contracting Officer (1) notifies the Contractor that funds are not available for contract performance for any subsequent program year, or (2) fails to notify the Contractor that funds are available for performance of the succeeding program year requirement. (b) Except for cancellation under this clause or termination under the Default clause, any reduction by the Contracting Officer in the requirements of this contract shall be considered a termination under the Termination for Convenience of the Government clause. (c) If cancellation under this clause occurs, the Contractor will be paid a cancellation charge not over the cancellation ceiling specified in the Schedule as applicable at the time of cancellation. (d) The cancellation charge will cover only (1) costs (i) incurred by the Contractor and/or subcontractor, (ii) reasonably necessary for performance of the contract, and (iii) that would have been equitably amortized over the entire multiyear contract period but, because of the cancellation, are not so amortized, and (2) a reasonable profit or fee on the costs. (e) The cancellation charge shall be computed and the claim made for it as if the claim were being made under the Termination for Convenience of the Government clause of this contract. The Contractor shall submit the claim promptly but no later than 1 year from the date (1) of notification of the nonavailability of funds, or (2) specified in the Schedule by which notification of the availability of additional funds fo

Source: eCFR, 48 CFR 52.217-2 (https://www.ecfr.gov/current/title-48/section-52.217-2)

Compliance Checklist

  • Cancellation shall occur by the date or within the time period specified in the Schedule, unless a later date is agreed to, if the Contracting Officer (1) notifies the Contractor that funds are not available for contract performance for any subsequent program year, or (2) fails to notify the Contractor that funds are available for performance of the succeeding program year requirement.
  • (b) Except for cancellation under this clause or termination under the Default clause, any reduction by the Contracting Officer in the requirements of this contract shall be considered a termination under the Termination for Convenience of the Government clause.
  • (e) The cancellation charge shall be computed and the claim made for it as if the claim were being made under the Termination for Convenience of the Government clause of this contract.
  • The Contractor shall submit the claim promptly but no later than 1 year from the date (1) of notification of the nonavailability of funds, or (2) specified in the Schedule by which notification of the availability of additional funds for the next succeeding program year is required to be issued, whichever is earlier, unless extensions in writing are granted by the Contracting Officer.
  • (g) The claim shall not include— (1) Labor, material, or other expenses incurred by the Contractor or subcontractors for performance of the canceled work; (2) Any cost already paid to the Contractor; (3) Anticipated profit or unearned fee on the canceled work; or (4) For service contracts, the remaining useful commercial life of facilities.
  • (i) Quantities added to the original contract through the Option clause of this contract shall be included in the quantity canceled for the purpose of computing allowable cancellation charges.

Flow-Down to Subcontractors

Flow-down required

This clause must be included in subcontracts with no subcontractors where the subcontractor will perform work covered by this clause. Typically appears in contract Section Section I.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.217-2

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.