52.232-10Payments Under Fixed-Price Architect-Engineer Contracts.

Researched by the BidStride Research Team

What This Clause Requires

FAR 52.232-10 — Payments Under Fixed-Price Architect-Engineer Contracts.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.232-10 Payments Under Fixed-Price Architect-Engineer Contracts. As prescribed in 32.111(c)(1), insert the following clause: Payments Under Fixed-Price Architect-Engineer Contracts (APR 2010) (a) Estimates shall be made monthly of the amount and value of the work and services performed by the Contractor under this contract which meet the standards of quality established under this contract. The estimates, along with any supporting data required by the Contracting Officer, shall be prepared by the Contractor and submitted along with its voucher. (b) After receipt of each substantiated voucher, the Government shall pay the voucher as approved by the Contracting Officer or authorized representative. The Contracting Officer shall require a withholding from amounts due under paragraph (a) of this clause of up to 10 percent only if the Contracting Officer determines that such a withholding is necessary to protect the Government's interest and ensure satisfactory completion of the contract. The amount withheld shall be determined based upon the Contractor's performance record under this contract. Whenever the Contracting Officer determines that the work is substantially complete and that the amount retained is in excess of the amount adequate for the protection of the Government, the Contracting Officer shall release the excess amount to the Contractor. (c) Upon satisfactory completion by the Contractor and final acceptance by the Contracting Officer of all the work done by the Contractor under the “Statement of Architect-Engineer Services”, the Contractor will be paid the unpaid balance of any money due for work under the statement, including all withheld amounts. (d) Before final payment under the contract, or before settlement upon termination of the contract, and as a condition precedent thereto, the Contractor shall execute and deliver to the Contracting Officer a release of all claims against the Government arising under or by virtue of this contract, other than an

Source: eCFR, 48 CFR 52.232-10 (https://www.ecfr.gov/current/title-48/section-52.232-10)

Compliance Checklist

  • As prescribed in 32.111(c)(1), insert the following clause: Payments Under Fixed-Price Architect-Engineer Contracts (APR 2010) (a) Estimates shall be made monthly of the amount and value of the work and services performed by the Contractor under this contract which meet the standards of quality established under this contract.
  • The estimates, along with any supporting data required by the Contracting Officer, shall be prepared by the Contractor and submitted along with its voucher.
  • (b) After receipt of each substantiated voucher, the Government shall pay the voucher as approved by the Contracting Officer or authorized representative.
  • The Contracting Officer shall require a withholding from amounts due under paragraph (a) of this clause of up to 10 percent only if the Contracting Officer determines that such a withholding is necessary to protect the Government's interest and ensure satisfactory completion of the contract.
  • The amount withheld shall be determined based upon the Contractor's performance record under this contract.
  • Whenever the Contracting Officer determines that the work is substantially complete and that the amount retained is in excess of the amount adequate for the protection of the Government, the Contracting Officer shall release the excess amount to the Contractor.
  • (d) Before final payment under the contract, or before settlement upon termination of the contract, and as a condition precedent thereto, the Contractor shall execute and deliver to the Contracting Officer a release of all claims against the Government arising under or by virtue of this contract, other than any claims that are specifically excepted by the Contractor from the operation of the release in amounts stated in the release.
  • (e) Notwithstanding any other provision in this contract, and specifically paragraph (b) of this clause, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions.

Flow-Down to Subcontractors

No flow-down required

This clause applies only to the prime contract and does not need to be flowed down to subcontractors.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.232-10

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.