52.232-22 — Limitation of Funds.
Researched by the BidStride Research Team
What This Clause Requires
FAR 52.232-22 — Limitation of Funds.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.
Official Regulation Text
52.232-22 Limitation of Funds. As prescribed in 32.706-2(b), insert the following clause. The 60-day period may be varied from 30 to 90 days and the 75 percent from 75 to 85 percent. “Task Order” or other appropriate designation may be substituted for “Schedule” wherever that word appears in the clause: Limitation of Funds (APR 1984) (a) The parties estimate that performance of this contract will not cost the Government more than (1) the estimated cost specified in the Schedule or, (2) if this is a cost-sharing contract, the Government's share of the estimated cost specified in the Schedule. The Contractor agrees to use its best efforts to perform the work specified in the Schedule and all obligations under this contract within the estimated cost, which, if this is a cost-sharing contract, includes both the Government's and the Contractor's share of the cost. (b) The Schedule specifies the amount presently available for payment by the Government and allotted to this contract, the items covered, the Government's share of the cost if this is a cost-sharing contract, and the period of performance it is estimated the allotted amount will cover. The parties contemplate that the Government will allot additional funds incrementally to the contract up to the full estimated cost to the Government specified in the Schedule, exclusive of any fee. The Contractor agrees to perform, or have performed, work on the contract up to the point at which the total amount paid and payable by the Government under the contract approximates but does not exceed the total amount actually allotted by the Government to the contract. (c) The Contractor shall notify the Contracting Officer in writing whenever it has reason to believe that the costs it expects to incur under this contract in the next 60 days, when added to all costs previously incurred, will exceed 75 percent of (1) the total amount so far allotted to the contract by the Government or, (2) if this is a cost-sharing contract, the am
Compliance Checklist
- (c) The Contractor shall notify the Contracting Officer in writing whenever it has reason to believe that the costs it expects to incur under this contract in the next 60 days, when added to all costs previously incurred, will exceed 75 percent of (1) the total amount so far allotted to the contract by the Government or, (2) if this is a cost-sharing contract, the amount then allotted to the contract by the Government plus the Contractor's corresponding share.
- The notice shall state the estimated amount of additional funds required to continue performance for the period specified in the Schedule.
- (d) Sixty days before the end of the period specified in the Schedule, the Contractor shall notify the Contracting Officer in writing of the estimated amount of additional funds, if any, required to continue timely performance under the contract or for any further period specified in the Schedule or otherwise agreed upon, and when the funds will be required.
- (f) Except as required by other provisions of this contract, specifically citing and stated to be an exception to this clause— (1) The Government is not obligated to reimburse the Contractor for costs incurred in excess of the total amount allotted by the Government to this contract; and (2) The Contractor is not obligated to continue performance under this contract (including actions under the Termination clause of this contract) or otherwise incur costs in excess of (i) the amount then allotted to the contract by the Government or, (ii) if this is a cost-sharing contract, the amount then allotted by the Government to the contract plus the Contractor's corresponding share, until the Contracting Officer notifies the Contractor in writing that the amount allotted by the Government has been increased and specifies an increased amount, which shall then constitute the total amount allotted by the Government to this contract.
- (g) The estimated cost shall be increased to the extent that (1) the amount allotted by the Government or, (2) if this is a cost-sharing contract, the amount then allotted by the Government to the contract plus the Contractor's corresponding share, exceeds the estimated cost specified in the Schedule.
- If this is a cost-sharing contract, the increase shall be allocated in accordance with the formula specified in the Schedule.
- (h) No notice, communication, or representation in any form other than that specified in subparagraph (f)(2) above, or from any person other than the Contracting Officer, shall affect the amount allotted by the Government to this contract.
- (i) When and to the extent that the amount allotted by the Government to the contract is increased, any costs the Contractor incurs before the increase that are in excess of (1) the amount previously allotted by the Government or, (2) if this is a cost-sharing contract, the amount previously allotted by the Government to the contract plus the Contractor's corresponding share, shall be allowable to the same extent as if incurred afterward, unless the Contracting Officer issues a termination or other notice and directs that the increase is solely to cover termination or other specified expenses.
- (j) Change orders shall not be considered an authorization to exceed the amount allotted by the Government specified in the Schedule, unless they contain a statement increasing the amount allotted.
- (k) Nothing in this clause shall affect the right of the Government to terminate this contract.
- If this contract is terminated, the Government and the Contractor shall negotiate an equitable distribution of all property produced or purchased under the contract, based upon the share of costs incurred by each.
Flow-Down to Subcontractors
No flow-down required
This clause applies only to the prime contract and does not need to be flowed down to subcontractors.
Frequently Asked Questions
FAR 52.232-22 (Limitation of Funds.) is a federal acquisition regulation clause that may be included in government contracts. It falls under the payment category.
FAR 52.232-22 is typically required when the contracting officer determines it's applicable to the specific procurement. Check the solicitation's Section I for included clauses.
Whether FAR 52.232-22 flows down depends on the specific clause language and contract type. Review the clause text for flow-down provisions.
This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.