52.232-25 — Prompt payment.
Researched by the BidStride Research Team
What This Clause Requires
FAR 52.232-25 — Prompt payment.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.
Official Regulation Text
52.232-25 Prompt payment. As prescribed in 32.908(c), insert the following clause: Prompt Payment (JAN 2017) Notwithstanding any other payment clause in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer (EFT). Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation. All days referred to in this clause are calendar days, unless otherwise specified. (However, see paragraph (a)(4) of this clause concerning payments due on Saturdays, Sundays, and legal holidays.) (a) Invoice payments —(1) Due date. (i) Except as indicated in paragraphs (a)(2) and (c) of this clause, the due date for making invoice payments by the designated payment office is the later of the following two events: (A) The 30th day after the designated billing office receives a proper invoice from the Contractor (except as provided in paragraph (a)(1)(ii) of this clause). (B) The 30th day after Government acceptance of supplies delivered or services performed. For a final invoice, when the payment amount is subject to contract settlement actions, acceptance is deemed to occur on the effective date of the contract settlement. (ii) If the designated billing office fails to annotate the invoice with the actual date of receipt at the time of receipt, the invoice payment due date is the 30th day after the date of the Contractor's invoice, provided the designated billing office receives a proper invoice and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements. (2) Certain food products and other payments. (i) Due dates on Contractor invoices for meat, meat food products, or fish; perishable agricultural commodities; and dairy products, edible fats or oils, and food products prepared from edible fats or oils are— (A) For
Compliance Checklist
- (ii) If the contract does not require submission of an invoice for payment ( e.g., periodic lease payments), the due date will be as specified in the contract.
- The Contractor shall prepare and submit invoices to the designated billing office specified in the contract.
- A proper invoice must include the items listed in paragraphs (a)(3)(i) through (a)(3)(x) of this clause.
- (vi) Name and address of Contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice of assignment).
- The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
- (A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
- (B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision ( e.g., 52.232-38, Submission of Electronic Funds Transfer Information with Offer), contract clause ( e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
- (C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
- (x) Any other information or documentation required by the contract ( e.g., evidence of shipment).
- (ii) The prompt payment regulations at 5 CFR 1315.10(c) do not require the Government to pay interest penalties if payment delays are due to disagreement between the Government and the Contractor over the payment amount or other issues involving contract compliance, or on amounts temporarily withheld or retained in accordance with the terms of the contract.
- The Government and the Contractor shall resolve claims involving disputes and any interest that may be payable in accordance with the clause at FAR 52.233-1, Disputes.
- (ii)(A) The Contractor shall support written demands for additional penalty payments with the following data.
- The Contractor shall— ( 1 ) Specifically assert that late payment interest is due under a specific invoice, and request payment of all overdue late payment interest penalty and such additional penalty as may be required; ( 2 ) Attach a copy of the invoice on which the unpaid late payment interest is due; and ( 3 ) State that payment of the principal has been received, including the date of receipt.
- (B) If there is no postmark or the postmark is illegible— ( 1 ) The designated payment office that receives the demand will annotate it with the date of receipt, provided the demand is received on or before the 40th day after payment was made; or ( 2 ) If the designated payment office fails to make the required annotation, the Government will determine the demand's validity based on the date the Contractor has placed on the demand, provided such date is no later than the 40th day after payment was made.
- If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall— (1) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the— (i) Circumstances of the overpayment ( e.g.
- For interim payments under this cost-reimbursement contract for services— (1) Paragraphs (a)(2), (a)(3), (a)(4)(ii), (a)(4)(iii), and (a)(5)(i) do not apply; (2) For purposes of computing late payment interest penalties that may apply, the due date for payment is the 30th day after the designated billing office receives a proper invoice; and (3) The contractor shall submit invoices for interim payments in accordance with paragraph (a) of FAR 52.216-7, Allowable Cost and Payment.
Flow-Down to Subcontractors
No flow-down required
This clause applies only to the prime contract and does not need to be flowed down to subcontractors.
Frequently Asked Questions
FAR 52.232-25 (Prompt payment.) is a federal acquisition regulation clause that may be included in government contracts. It falls under the payment category.
FAR 52.232-25 is typically required when the contracting officer determines it's applicable to the specific procurement. Check the solicitation's Section I for included clauses.
Whether FAR 52.232-25 flows down depends on the specific clause language and contract type. Review the clause text for flow-down provisions.
This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.