52.234-2Notice of Earned Value Management System—Preaward Integrated Baseline Review.

Researched by the BidStride Research Team

What This Clause Requires

FAR 52.234-2 — Notice of Earned Value Management System—Preaward Integrated Baseline Review.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.234-2 Notice of Earned Value Management System—Preaward Integrated Baseline Review. As prescribed in 34.203(a) use the following provision: Notice of Earned Value Management System—Preaward Integrated Baseline Review (NOV 2016) (a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at time of solicitation). (b) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS guidelines. (1) The plan shall— (i) Describe the EVMS the offeror intends to use in performance of the contracts; (ii) Distinguish between the offeror's existing management system and modifications proposed to meet the guidelines; (iii) Describe the management system and its application in terms of the EVMS guidelines; (iv) Describe the proposed procedure for administration of the guidelines, as applied to subcontractors; and (v) Provide documentation describing the process and results of any third-party or self-evaluation of the system's compliance with the EVMS guidelines. (2) The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan. (3) The Government will review and approve the offeror's plan for an EVMS before contract award. (4) The offeror's EVMS plan must provide milestones that indicate when the offeror anticipates that the EVM system will be compliant with the EIA-748 guidelines. (c) Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected subject to the guidelines. The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS guidelines. (d) The Governm

Source: eCFR, 48 CFR 52.234-2 (https://www.ecfr.gov/current/title-48/section-52.234-2)

Compliance Checklist

  • As prescribed in 34.203(a) use the following provision: Notice of Earned Value Management System—Preaward Integrated Baseline Review (NOV 2016) (a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at time of solicitation).
  • (b) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS guidelines.
  • (1) The plan shall— (i) Describe the EVMS the offeror intends to use in performance of the contracts; (ii) Distinguish between the offeror's existing management system and modifications proposed to meet the guidelines; (iii) Describe the management system and its application in terms of the EVMS guidelines; (iv) Describe the proposed procedure for administration of the guidelines, as applied to subcontractors; and (v) Provide documentation describing the process and results of any third-party or self-evaluation of the system's compliance with the EVMS guidelines.
  • (2) The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.
  • (4) The offeror's EVMS plan must provide milestones that indicate when the offeror anticipates that the EVM system will be compliant with the EIA-748 guidelines.
  • (c) Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected subject to the guidelines.
  • The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS guidelines.

Flow-Down to Subcontractors

No flow-down required

This clause applies only to the prime contract and does not need to be flowed down to subcontractors.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.234-2

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.