52.236-11 — Use and Possession Prior to Completion.
Researched by the BidStride Research Team
What This Clause Requires
FAR 52.236-11 — Use and Possession Prior to Completion.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.
Official Regulation Text
52.236-11 Use and Possession Prior to Completion. As prescribed in 36.511, insert the following clause: Use and Possession Prior to Completion (APR 1984) (a) The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use shall not be deemed an acceptance of any work under the contract. (b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government's possession or use, notwithstanding the terms of the clause in this contract entitled Permits and Responsibilities. If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly. (End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
Compliance Checklist
- As prescribed in 36.511, insert the following clause: Use and Possession Prior to Completion (APR 1984) (a) The Government shall have the right to take possession of or use any completed or partially completed part of the work.
- Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use.
- However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract.
- The Government's possession or use shall not be deemed an acceptance of any work under the contract.
- (b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government's possession or use, notwithstanding the terms of the clause in this contract entitled Permits and Responsibilities.
- If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.
Flow-Down to Subcontractors
No flow-down required
This clause applies only to the prime contract and does not need to be flowed down to subcontractors.
Frequently Asked Questions
FAR 52.236-11 (Use and Possession Prior to Completion.) is a federal acquisition regulation clause that may be included in government contracts. It falls under the construction category.
FAR 52.236-11 is typically required when the contracting officer determines it's applicable to the specific procurement. Check the solicitation's Section I for included clauses.
Whether FAR 52.236-11 flows down depends on the specific clause language and contract type. Review the clause text for flow-down provisions.
This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.