52.242-15 — Stop-Work Order.
Researched by the BidStride Research Team
What This Clause Requires
FAR 52.242-15 — Stop-Work Order.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.
Official Regulation Text
52.242-15 Stop-Work Order. As prescribed in 42.1305(b), insert the following clause. The 90-day period stated in the clause may be reduced to less than 90 days. Stop-Work Order (AUG 1989) (a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either— (1) Cancel the stop-work order; or (2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract. (b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if— (1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract; and (2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon a proposal submitted at any time before final payment
Compliance Checklist
- Stop-Work Order (AUG 1989) (a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree.
- The order shall be specifically identified as a stop-work order issued under this clause.
- Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage.
- Within a period of 90 days after a stop-work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either— (1) Cancel the stop-work order; or (2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.
- (b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work.
- The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if— (1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract; and (2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon a proposal submitted at any time before final payment under this contract.
- (c) If a stop-work order is not canceled and the work covered by the order is terminated for the conveninece of the Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement.
- (d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.
Flow-Down to Subcontractors
No flow-down required
This clause applies only to the prime contract and does not need to be flowed down to subcontractors.
Frequently Asked Questions
FAR 52.242-15 (Stop-Work Order.) is a federal acquisition regulation clause that may be included in government contracts. It falls under the contract-admin category.
FAR 52.242-15 is typically required when the contracting officer determines it's applicable to the specific procurement. Check the solicitation's Section I for included clauses.
Whether FAR 52.242-15 flows down depends on the specific clause language and contract type. Review the clause text for flow-down provisions.
This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.