52.243-1Changes—Fixed-Price.

Researched by the BidStride Research Team

What This Clause Requires

FAR 52.243-1 — Changes—Fixed-Price.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.243-1 Changes—Fixed-Price. As prescribed in 43.205(a)(1), insert the following clause. The 30-day period may be varied according to agency procedures. Changes—Fixed-Price (AUG 1987) (a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following: (2) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications. (2) Method of shipment or packing. (3) Place of delivery. (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract. (c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract. (d) If the Contractor's proposal includes the cost of property made obsolete or excess by the change, the Contracting Officer shall have the right to prescribe the manner of the disposition of the property. (e) Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. (End of clause) Alternate I (APR 1984). If the requirement is for services, other than architect-engineer or other professional services, and no supplies are to be furnished, substitute the following paragraph (a) for paragraph (a) of the basic clause: (a) The Contracting Officer may at any time, by written order, and

Source: eCFR, 48 CFR 52.243-1 (https://www.ecfr.gov/current/title-48/section-52.243-1)

Compliance Checklist

  • (b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
  • (c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order.
  • (d) If the Contractor's proposal includes the cost of property made obsolete or excess by the change, the Contracting Officer shall have the right to prescribe the manner of the disposition of the property.
  • (e) Failure to agree to any adjustment shall be a dispute under the Disputes clause.
  • However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
  • (f) No services for which an additional cost or fee will be charged by the Contractor shall be furnished without the prior written authorization of the Contracting Officer.
  • (b) If any such change causes an increase or decrease in the cost of, or time required for, performing this contract, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in (1) the contract price, the time of performance, or both; and (2) other affected terms of the contract, and shall modify the contract accordingly.

Flow-Down to Subcontractors

No flow-down required

This clause applies only to the prime contract and does not need to be flowed down to subcontractors.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.243-1

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.