52.243-2Changes—Cost-Reimbursement.

Researched by the BidStride Research Team

What This Clause Requires

FAR 52.243-2 — Changes—Cost-Reimbursement.. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.243-2 Changes—Cost-Reimbursement. As prescribed in 43.205(b)(1), insert the following clause. The 30-day period may be varied according to agency procedures. Changes—Cost-Reimbursement (AUG 1987) (a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following: (1) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications. (2) Method of shipment or packing. (3) Place of delivery. (b) If any such change causes an increase or decrease in the estimated cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, or otherwise affects any other terms and conditions of this contract, the Contracting Officer shall make an equitable adjustment in the (1) estimated cost, delivery or completion schedule, or both; (2) amount of any fixed fee; and (3) other affected terms and shall modify the contract accordingly. (c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract. (d) Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. (e) Notwithstanding the terms and conditions of paragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific written modification of the contract indicating the new con

Source: eCFR, 48 CFR 52.243-2 (https://www.ecfr.gov/current/title-48/section-52.243-2)

Compliance Checklist

  • (b) If any such change causes an increase or decrease in the estimated cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, or otherwise affects any other terms and conditions of this contract, the Contracting Officer shall make an equitable adjustment in the (1) estimated cost, delivery or completion schedule, or both; (2) amount of any fixed fee; and (3) other affected terms and shall modify the contract accordingly.
  • (c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order.
  • (d) Failure to agree to any adjustment shall be a dispute under the Disputes clause.
  • However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
  • (e) Notwithstanding the terms and conditions of paragraphs (a) and (b) above, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific written modification of the contract indicating the new contract estimated cost and, if this contract is incrementally funded, the new amount allotted to the contract.
  • Until this modification is made, the Contractor shall not be obligated to continue performance or incur costs beyond the point established in the Limitation of Cost or Limitation of Funds clause of this contract.

Flow-Down to Subcontractors

No flow-down required

This clause applies only to the prime contract and does not need to be flowed down to subcontractors.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.243-2

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.