52.249-5Termination for Convenience of the Government (Educational and Other Nonprofit Institutions).

Researched by the BidStride Research Team

What This Clause Requires

FAR 52.249-5 — Termination for Convenience of the Government (Educational and Other Nonprofit Institutions).. This clause is part of the Federal Acquisition Regulation and may be included in government contracts as a solicitation provision or contract clause.

Official Regulation Text

52.249-5 Termination for Convenience of the Government (Educational and Other Nonprofit Institutions). As prescribed in 49.502(d), insert the following clause: Termination for Convenience of the Government (Educational and Other Nonprofit Institutions) (AUG 2016) (a) The Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government's interest. The Contracting Officer shall terminate by delivering to the Contractor a Notice of Termination specifying the extent of termination and the effective date. (b) After receipt of a Notice of Termination and except as directed by the Contracting Officer, the Contractor shall immediately proceed with the following obligations: (1) Stop work as specified in the notice. (2) Place no further subcontracts or orders (referred to as subcontracts in this clause), except as necessary to complete the continued portion of the contract. (3) Terminate all applicable subcontracts and cancel or divert applicable commitments covering personal services that extend beyond the effective date of termination. (4) Assign to the Government, as directed by the Contracting Officer, all right, title, and interest of the Contractor under the subcontracts terminated, in which case the Government shall have the right to settle or pay any termination settlement proposal arising out of those terminations. (5) With approval or ratification to the extent required by the Contracting Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; approval or ratification will be final for purposes of this clause. (6) Transfer title (if not already transferred) and, as directed by the Contracting Officer, deliver to the Government any information and items that, if the contract had been completed, would have been required to be furnished, including (i) materials or equipment produced

Source: eCFR, 48 CFR 52.249-5 (https://www.ecfr.gov/current/title-48/section-52.249-5)

Compliance Checklist

  • The Contracting Officer shall terminate by delivering to the Contractor a Notice of Termination specifying the extent of termination and the effective date.
  • (b) After receipt of a Notice of Termination and except as directed by the Contracting Officer, the Contractor shall immediately proceed with the following obligations: (1) Stop work as specified in the notice.
  • (4) Assign to the Government, as directed by the Contracting Officer, all right, title, and interest of the Contractor under the subcontracts terminated, in which case the Government shall have the right to settle or pay any termination settlement proposal arising out of those terminations.
  • (5) With approval or ratification to the extent required by the Contracting Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; approval or ratification will be final for purposes of this clause.
  • (6) Transfer title (if not already transferred) and, as directed by the Contracting Officer, deliver to the Government any information and items that, if the contract had been completed, would have been required to be furnished, including (i) materials or equipment produced, in process, or acquired for the work terminated and (ii) completed or partially completed plans, drawings, and information.
  • (9) Use its best efforts to sell, as directed or authorized by the Contracting Officer, termination inventory other than that retained by the Government under subparagraph (b)(6) of this clause; provided, however, that the Contractor (i) is not required to extend credit to any purchaser and (ii) may acquire the property under the conditions prescribed by, and at prices approved by, the Contracting Officer.
  • (c) The Contractor shall submit complete termination inventory schedules no later than 120 days from the effective date of termination, unless extended in writing by the Contracting Officer upon written request of the Contractor within this 120-day period.
  • (d) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer.
  • The Contractor shall submit the proposal promptly but no later than 1 year from the effective date of termination unless extended in writing by the Contracting Officer upon written request of the Contractor within this 1-year period.
  • If the Contractor fails to submit the termination settlement proposal within the time allowed, the Contracting Officer may determine, on the basis of information available, the amount, if any, due the Contractor because of the termination and shall pay the amount determined.
  • The contract shall be amended and the Contractor paid the agreed amount.
  • 1001), as in effect on the date of the contract, shall govern all costs claimed, agreed to, or determined under this clause; however, if the Contractor is not an educational institution and is a nonprofit organization (as defined in the OMB Uniform Guidance at 2 CFR part 200), the cost principles and procedures in subpart 31.7 of the FAR, Contracts with Nonprofit Organizations, shall apply; unless the Contractor is a nonprofit institution listed in the OMB Uniform Guidance at 2 CFR part 200, appendix VIII, as exempted from the cost principles in subpart E, in which case the cost principles at FAR 31.2 for commercial organizations shall apply to such contractor.

Flow-Down to Subcontractors

Flow-down required

This clause must be included in subcontracts with no subcontractors where the subcontractor will perform work covered by this clause. Typically appears in contract Section Section I.

Frequently Asked Questions

BidStride automatically scans your RFPs for 52.249-5

Stop hunting through solicitations manually. BidStride identifies every FAR and DFARS clause in your RFP, flags risk level, and surfaces compliance requirements before you submit your bid.

This summary is for informational purposes only and reflects the BidStride Research Team's plain-English interpretation of the regulation. It is not legal advice and does not constitute an attorney-client relationship. Always consult the official Federal Acquisition Regulation (FAR) or Defense Federal Acquisition Regulation Supplement (DFARS) text and qualified legal counsel for compliance decisions.